The visit has taken place. Two non-conformities were identified — details in report No. TA-2026-048/04. Please provide the concrete sampling acts.
- report-048-04.pdf2.4 MB
Facility
01 · Progress
62% Work performed — confirmed by inspection
The substructure works have been confirmed. Report No. TA-2026-048/01.
The reinforcement and concrete conform to the design. Report No. TA-2026-048/02.
The quantities have been confirmed. Report No. TA-2026-048/03.
Two non-conformities were identified during the last visit — see below.
The inspection will begin once the frame is completed.
Power supply, water and sewerage, heating and ventilation.
02 · Non-conformities
| № | Description | Date identified | Deadline | Status |
|---|---|---|---|---|
| NC-07 | On the 11th floor the reinforcement cover is thinner than specified in the design | 24.10.2026 | 07.11.2026 | Open |
| NC-06 | No concrete sampling act has been submitted for 3 pours | 24.10.2026 | 31.10.2026 | Open |
| NC-05 | The scaffolding anchorage does not conform to the scheme | 19.09.2026 | 26.09.2026 | Closed |
03 · Workspace
The visit has taken place. Two non-conformities were identified — details in report No. TA-2026-048/04. Please provide the concrete sampling acts.
We will retrieve the acts and upload them tomorrow. Corrective work on the protective layer is under way.
Thank you. Once corrected, please provide photographic records — we will re-check at the visit on 07.11.